Before starting the construction of a residential building, a site has to be owned at the desired place. A plan to be prepared as per the need of the person and necessary approval has to be obtained. The site clearance has to be done and then the actual work has to be started. The sequence of operations is discussed below.

 

Step 1: Excavation of foundation

 

Step 2: Base concrete

 

Step 3:  Masonry construction

 

Step 4: Plinth beam construction

 

Step 5: Sand filling up to plinth level

 

Step 6: Preparation of doors and windows

 

Step 7: Floor concrete

 

Step 8: Starting of superstructure construction

 

Step 9: Fixing doors and windows

 

Step 10: Finishing superstructure upto lintel level

 

Step 11: Construction of lintels and sunshades

 

Step 12: Brickwork up to ceiling and roof

 

Step 13: Electrical pipe and board fixing

 

Step 14: Roof casting

 

Step 15: Removal of formwork

 

Step 16: Finishing all plumbing work

 

Step 17: Plastering

 

Step 18: Floor finishing

 

Step 19: Construction of compound or boundary walls

 

Step 20: Fixing doors and window shutters

 

Step 21: Electrical fittings

 

Step 22: Painting and polishing.

 

Above discussed sequence of operations is shown in a flow diagram, below table

construction-sequence-of-residential-building





 

 

Excavation for foundation

 

 

 

 

 

 

 

 

Base concrete and masonry construction

 

 

 

 

 

 

 

 

Plinth beam construction and sand filling

 

 

 

 

 

 

 

 

Floor concrete and starting of superstructure construction

 

 

 

 

 

 

Preparation of doors and windows

Fixing doors and windows

 

 

 

 

 

 

 

 

 

 

 

 

 

Finishing superstructure upto lintel level

 

 

 

 

 

 

 

 

Construction of lintels and sunshades

 

 

 

 

 

 

Electrical pipe and board fixing

Brickwork up to ceiling and roof casting

 

 

Electrical points and fixing

 

Remove formwork and plastering

Plumbing work



Construction Sequence Of Residential Building


Construction Sequence Of Residential Building


If you find 

 

This information is helpful, please share it.

 

Thanks! For reading the article.   

1 comment:

  1. I thoroughly enjoyed reading about the 'Construction Sequence of Residential Building.' Annai Bharath Housing's commitment to precision and adherence to construction sequences is commendable. This article provides valuable insights that align with their construction principles.

    ReplyDelete

LCETED - "WHATSAPP GROUP"

For Instant updates Join our Whatsapp Group. Save our Whatsapp contact +919840140396 as LCETED and Send us a message “JOIN”

Post Bottom Ad