Guide to Prepare BOQ for Sanitary
Wares, Drainage, and Water Supply Systems
Preparing a Bill of Quantities (BOQ) is essential for accurate cost
estimation and compliance in construction projects. This guide provides
detailed steps to prepare a BOQ for sanitary wares, accessories, internal
drainage, and water supply pipes and fittings.
How to Prepare a BOQ for Sanitary
Wares and Accessories?
Sanitary wares and accessories are key components of plumbing
installations. The BOQ must include detailed descriptions, units of measurement
(UoM), and instructions for supply, installation, and testing.
Preamble for Sanitary Wares and
Accessories
The work shall include cutting making of walls and floors etc. The rates
quoted shall include cost of necessary consumables like brass screws, CP
extension nipple of approved make, dia and length, wooden plugs, white cement,
sealants etc. Only drilling machines shall be used for making the holes in the
walls for fixing, no wall jumper and hammer will be allowed.
How to Prepare a BOQ for European
Water Closet (EWC)?
- Description: Supply and fixing of WHITE
     coloured vitreous china Wall mounted EUROPEAN WATER CLOSET with concealed
     flush valve with ‘P’ or ‘S’ trap, complete with solid seat with cover,
     C.P. hinges and rubber buffers, cold water connection pipe including, C.P.
     bolts and nuts etc. The work shall include cutting and making good the
     walls and floors etc. - In toilets.
 - UoM: Nos
 
How to Prepare a BOQ for CP Health
Faucet?
- Description: Supply and fixing of 15 mm CP
     health faucet of approved make with necessary CP flexible hose 1250 mm
     flexible tube, 15mm dia brass C.P. Angle stop cock with flange, CP wall
     flange etc., complete.
 - UoM: Nos
 
How to Prepare a BOQ for Sensor
Urinal?
- Description: Supply and fixing of white
     colour vitreous china Urinal with integrated Sensor with partition for
     flushing with in built waste grating, C.P. cast brass bottle trap with
     extension piece including CI/MS bracket wall flanges, flush piping,
     flexible hose, extension nipples, Sensing range of minimum 20cm, Control
     box (AC/DC) (6V AA Alkaline battery) etc complete.
 - UoM: Nos
 
How to Prepare a BOQ for Below Counter
Washbasin?
- Description: Supply, Installation, fixing,
     testing and commissioning of WHITE coloured vitreous china Below counter
     rectangular Washbasin with brackets / G.I. rag bolts and nuts painted,
     32mm dia brass C.P. waste coupling, (heavy) 32mm dia brass C.P. bottle
     trap, 15mm dia brass C.P. Angle stop cock with flange, 15mm dia brass C.P.
     cold water connecting pipe, etc. The work shall include required extension
     nipples, cutting / chasing and making good the walls and floors. (Location
     - Hand wash).
 - UoM: Nos
 
How to Prepare a BOQ for Rectangular
Washbasin?
- Description: Supply, Installation, fixing,
     testing and commissioning of WHITE coloured vitreous china RECTANGULAR
     WASH BASIN with brackets / G.I. rag bolts and nuts painted, 32mm dia brass
     C.P. waste coupling, (heavy) 32mm dia brass C.P. bottle trap, 15mm dia
     brass C.P. Angle stop cock with flange, 15mm dia brass C.P. cold water
     connecting pipe, etc. The work shall include required extension nipples,
     cutting / chasing and making good the walls and floors. (Location - Hand
     wash).
 - UoM: Nos
 
How to Prepare a BOQ for Sensor Pillar
Cock?
- Description: Supply, Installation, fixing,
     testing and commissioning of wash basin table mounted SENSOR TYPE PILLAR
     COCK, required cp flanges, angle cock, flexible hose, extension nipples,
     Sensing range of minimum 20cm, Control box operated by (AC/DC) (6V AA
     Alkaline battery) etc complete.
 - UoM: Nos
 
How to Prepare a BOQ for Swivel Spout?
- Description: Supply, Installation, fixing,
     testing and commissioning of wash basin table mounted Swivel spout,
     required cp flanges, angle cock, flexible hose, extension nipples, etc
     complete. (Location - Pantry).
 - UoM: Nos
 
How to Prepare a BOQ for Storage Water
Heater?
- Description: Supply, fixing and testing of
     electrically operated storage 25 L water heater inner container made from
     copper or stainless steel including the installation safety valve, vacuum
     relief valve, neon lamp, mounting brackets, installing in position with coach
     screws or bolts, nuts, testing, commissioning, etc, complete. 15mm dia
     Angle stop cock with wall flange, 15mm dia C.P. hot and cold water
     connection pipe including, C.P. bolts and nuts etc. The work shall include
     cutting and making good the walls and floors etc.
 - UoM: Nos
 
How to Prepare a BOQ for Stainless
Steel Sink?
- Description: Supply and fixing of Stainless
     steel Single bowl sink without drain board, manufactured from 1 mm thick
     stainless steel, 18G high grade indestructible chrome nickel steel with
     top quality polish, 1 no. 50 mm dia CP waste pipe connect with 'P' trap of
     minimum 40mm water seal, 20mm dia CP swivel spout wall mounted type and
     necessary wall flanges etc., complete.
 - UoM: Nos
 
How to Prepare a BOQ for Tissue Paper
Dispenser?
- Description: Supply and fixing of Automatic
     tissue paper dispenser with PVC rawl plug & C.P. brass screw complete
     as required.
 - UoM: Nos
 
How to Prepare a BOQ for Robe Hook?
- Description: Supply and fixing of Robe hook
     with PVC rawl plug & C.P. brass screw complete as required.
 - UoM: Nos
 
How to Prepare a BOQ for Liquid Soap
Dispenser?
- Description: Supply and fixing of Automatic
     liquid soap dispenser with PVC rawl plug & C.P. brass screw complete
     as required.
 - UoM: Nos
 
How to Prepare a BOQ for Hand Dryer?
- Description: Supply and fixing of solid
     state, no touch operating, fully hygienic hand drier of approved shade
     with single blower, with time delay, summer & winter control, music
     while drying, volume ON/OFF controls.
 - UoM: Nos
 
How to Prepare a BOQ for Garbodrain?
- Description: Supply, fixing and testing of
     Garbodrain, including all fittings, should be anti-jam impellers made of
     SS 304 for efficient grinding & corrosion free, run with AC power
     supply.
 - UoM: Nos
 
How to Prepare a BOQ for Grease
Separator?
- Description: Supply, fixing and testing of
     prefabricated gravity Grease seperator of flow rate 0.8 lps, with
     integrated sludge & grease trap, Connection for inlet and outlet
     should be minimum 50 mm dia, For free-standing installation in frost-proof
     areas, odour-proof sealed, with removable cover and fastening ring,
     Separate Grease storage tank with hand pump of capacity 10 Litres
     (Operating side Left / Right to be decided before order).
 - UoM: Nos
 - Note: Separator should be inspected
     and cleaned during every 1 or 2 days, Installed in access space for
     removable of grease. Separated grease should not be discharge in the drain
     to STP.
 
How to Prepare a BOQ for Grey Water
Lifting Station?
- Description: Supply & commissioning of a
     floor standing grey water lifting station with (1 working + 1 standby:
     Voltage: 220-240V, Frequency: 50-60 Hz, Motor power: 750 W, 2 multichannel
     impeller pumps, Maximum pumping head 15 m, Maximum flow rate of 16 m3/h, 2
     x 40 / 50 / 80 mm ext. side inlets, 1 x 50 mm ventilation pipe, Discharge
     diameter of 50 mm ext., Maximum incoming water temperature: 90°C (5
     minutes maximum), Tank volume: 34 L, Pneumatic switches, Deported control
     panel (with LED light and manual override button), Accessories (fixing
     kit, non-return valve and connectors). (Location: Cafeteria)
 - UoM: Nos
 
How to Prepare a BOQ for Grab Bars?
- Description: Supply, fixing and testing of
     Fixed grab bar and rotated grab bar, Fixing screw, etc., complete.
     (Location: Physically challenged toilet)
 - UoM: Nos
 
How to Prepare a BOQ for Internal
Drainage and Water Supply Pipes & Fittings?
Internal drainage and water supply systems require precise specifications
for pipes, fittings, and installation methods. The BOQ must reflect these
details accurately.
How to Prepare a BOQ for UPVC Soil,
Waste, and Vent Pipes?
- Description: Supply, fixing, testing and
     commissioning of UPVC soil, waste and vent pipe confirming to IS 13592 of
     SWR quality 6 kg / sq.cm pressure rated 10mm, including all fittings, like
     Bends, Tees, Elbows, Collars, junction, inspection doors, cowls, offsets,
     access pipes, jointing with rubber ring / solvent cement followed by
     application of leak proof adhesive like FRP paste, fixed to wall with
     properly fabricated MS bracket of suitable size, Soil & waste pipe
     line laid inside the sunken slab. (Pipes Running inside the sunken Slab
     & Shaft etc) 
 - a) 75mm dia (6kg/sq.cm pressure rated - Type - B) - UoM:
      Rmt
 - b) 110mm dia (6kg/sq.cm pressure rated - Type - B) - UoM:
      Rmt
 - c) 160mm dia (6kg/sq.cm pressure rated - Type - B) - UoM:
      Rmt
 - d) 200mm dia (6kg/sq.cm pressure rated - Type - B) - UoM:
      Rmt
 
How to Prepare a BOQ for UPVC Waste
Pipes?
- Description: Supply, fixing, testing and
     commissioning of UPVC waste pipe of agricultural sereis conforming to IS
     4985, including all fittings like tees, elbows, bends, collars, coupling,
     etc jointing with solvent cement followed by application of leak proof
     adhesive like FRP paste laid on floors inside the toilets to the required
     slope including making necessary bores in walls / foundations / concrete
     slab as applicable, making good the bores with CM 1:3 or cement concrete
     as applicable, curing etc., complete. 
 - a) 40mm dia (10kg / sq.cm) - UoM: Rmt
 - b) 50mm dia (10kg / sq.cm) - UoM: Rmt
 
How to Prepare a BOQ for PVC Floor
Trap?
- Description: Supply, fixing and testing of
     PVC floor-trap 110 dia with necessory of multitrap connection (heavy duty
     hinged type) with brass CP frame & cover (150 mm x 150 mm). Trap of
     100 mm dia inlet and 75 mm dia outlet fixed on a bed of cement concrete
     etc.complete. (The frame and grating shall be approved by Architects)
     (Location: Toilet, Washbasin)
 - UoM: Nos
 
How to Prepare a BOQ for PVC P-Trap?
- Description: Supply, fixing and testing of
     PVC P-trap 110 dia with necessory of 50 dia multitrap connection (heavy
     duty) with brass CP frame & cover (150 mm x 150 mm). Trap of 100 mm
     dia inlet and 100 mm dia outlet fixed on a bed of cement concrete
     etc.complete. (The frame and grating shall be approved by Architects)
     (Location: Urinal)
 - UoM: Nos
 
How to Prepare a BOQ for CP Grating
Cover?
- Description: Supply, fixing and testing of
     CP grating cover (150mmx150 mm). for drain outlet etc., complete. (The
     frame and grating shall be approved by Architects)
 - UoM: Nos
 
How to Prepare a BOQ for CP Floor
Cleanout?
- Description: Supply, fixing and testing of
     CP Floor cleanout (150mmx150 mm). For removing Clogging, etc., complete.
     (The frame and grating shall be approved by Architects)
 - UoM: Nos
 
How to Prepare a BOQ for CPVC Pipes?
- Description: Supplying, installing, fixing,
     jointing, testing and commissioning of approved make Chlorinated Polyvinyl
     Chloride pipes (CPVC) up to 50 mm dia SDR.13.5, ASTM CTS, and above 50 mm
     dia CPVC schedule 40 ASTM IPS. Fittings up to 50 mm dia SDR 13.5. The fittings
     and specials such as tees, elbows, couplers, bends, enlargers etc., with
     CPVC brass threaded combination / transition specials such as male
     adapters brass threaded female adapters, brass FPT Tee, Brass FPT elbow
     etc., where connection with metal is to be made including necessary
     drilling holes, chasing walls and making the same good in geru mixed
     cement mortar 1:1 restore the same original condition neatly as directed
     by the Engineer in-charge. Joints to be made with CPVC solvent cement up
     to 50 mm dia as per ASTM D-2846 and above 50 mm dia primer P-70, and
     solvent confirming to ASTMF-4931 / 724. (Pipe running on ceiling, inside
     the wall concealed for cold water supply) 
 - a) 20 mm dia - UoM: Rmt
 - b) 25 mm dia - UoM: Rmt
 - c) 32 mm dia - UoM: Rmt
 - d) 40 mm dia - UoM: Rmt
 - e) 50 mm dia - UoM: Rmt
 
How to Prepare a BOQ for Brass Ball
Valves?
- Description: Supplying, installing, fixing,
     jointing, testing and commissioning of Brass ball valves including unions
     etc., Complete 
 - a) 20 mm dia (Screwed ends) - UoM: Nos
 - b) 25 mm dia (Screwed ends) - UoM: Nos
 - c) 32 mm dia (Screwed ends) - UoM: Nos
 - d) 40 mm dia (Screwed ends) - UoM: Nos
 - e) 50 mm dia (Screwed ends) - UoM: Nos
 
How to Prepare a BOQ for Brass Y/Pot
Strainer?
- Description: Supplying, installing, fixing,
     jointing, testing and commissioning of brass `Y' / pot stainer screw type
     tested to 20 kg / sq.cm. 
 - a) 50 mm dia - UoM: Nos
 
How to Prepare a BOQ for Brass
Electromagnetic Flow Meter?
- Description: Supplying, installing, fixing,
     jointing, testing and commissioning of brass Electromagnetic flow meter
     screw type tested to 20 kg / sq.cm. 
 - a) 32 mm dia - UoM: Nos
 - b) 40 mm dia - UoM: Nos
 
How to Prepare a BOQ for Brass
Pressure Reducing Valve?
- Description: Supplying, installing, fixing,
     jointing, testing and commissioning of brass Pressure reducing valve screw
     type tested to 20 kg / sq.cm. 
 - a) 32 mm dia - UoM: Nos
 - b) 40 mm dia - UoM: Nos
 
How to Prepare a BOQ for MS Brackets
and Supports?
- Description: Supplying and fixing MS slotted
     angle iron brackets, hangers, MS grip bilts, universal clamps with
     threaded rod, supports with necessary drilling holes to suit the insertion
     of pipe clamps, deburring etc., as per detailed drawing for supporting
     soil, waste and rain water pipes and water supply pipes in shafts with
     suitable MS clamps, bolts, anchor bolts, nuts and washers fixed on shaft
     walls/outer walls etc. The quoted rate shall include with the cost of
     brackets galvanizing with zinc alloy of 0.08 mm thick conformed to IS 1239
     etc., complete as directed by the employer.
 - UoM: Kg
 
Conclusion
This guide outlines how to prepare a BOQ for sanitary wares, accessories,
and internal drainage and water supply systems, ensuring compliance with
project standards. Each item includes specific descriptions and UoM for clarity
and accuracy.