Quality Inspection Checklist for Firefighting Works - teamlceted -lceted LCETED INSTITUTE FOR CIVIL ENGINEERS

Post Top Ad

Apr 30, 2023

Quality Inspection Checklist for Firefighting Works - teamlceted


Quality Inspection Checklist for Firefighting Works | Building Inspection Checklist for Fire and General Safety | Inspection Checklist Fire Protection Equipment


In this article, we have discussed and enclosed the quality Inspection checklist for firefighting Works (FFS) in construction to be used by civil engineers


Quality Inspection Checklist on Installation of Fire Extinguisher

Before Installation                               

1. Are the fire extinguishers delivered to the site of the required make and type?   

                    

2. Is the pressure level in the extinguishers as per the specifications?            

             

3. Have the locations for installation of Fire extinguishers been identified as per drawings                                                  

After Installation                           

1. Travel distance to the nearest unit not exceeding 23 meters (per IRI).

                    

2. Enough 10C rated units provided where charged electrical equipment will be installed

 

3. Is the testing and commissioning of the system complete?  

   

Checklist on Installation of Fire Extinguisher

    

 

Quality Inspection Checklist on Pressure Testing of Pipes

Before Installation

1. Mark the length of the pipe under test on a relevant drawing, with the date and time of the test.

 

2. Ensure all the open ends have been plugged in before starting the test. A pneumatic pressure test (at low pressure) may be conducted.

 

3. Ensure all the isolation valves are closed and locked

 

4. Ensure the pressurization pump is removed and the feed valve is locked after reaching the test pressure.

a. Test pressure

b. Duration:

From:

To:

c. Visual check for the leakages

d. Observations at the end of the test         

Checklist on Pressure Testing of Pipes



   

 

Quality Inspection Checklist on Installation of Sprinkler

Before Installation - Ensure only a qualified welder is working on the job.

1. Check the piping is done as per the approved shop drawing.

 

2. The pipe diameter, type of fittings is as per spec.

 

3. All the pipe joints below 50mm diameter shall be threaded type only.

 

4. The bottom-of-pipe levels are as per the coordinated services drawing / shop drawing.

 

5. Pipe support is provided as per spec. Minimum at every 2.5 meters. The support shall hang the pipes stress-free.

 

6. Ensure only approved welding electrodes had been used.

 

7. Radiographic test to be done randomly on welded joints. Attach test report.

 

8. Visual inspection of welded joints for neatness.

 

9. Pressure testing is to be done before painting the pipe

 

10. Approved primer and paint are uniformly applied. No coats as per spec. Apply touch-up paint wherever necessary.

 

11. Tapping for sprinkler drops is taken from the top of the branch header (in case of FM-approved piping only)

 

12. All sprinkler drops are exactly centered with the grid tiles. Ensure that a template is used.

 

13. Ensure valves are provided at the correct locations

 

14. Provision for draining the pipeline is done. A pressure gauge, a ball valve, and a flexible PVC pipe to the nearest drain point shall be provided. The same shall be removed after the successful commissioning of the system.

 

15. Installed test sprinkler at a convenient location for inspection by the Fire Authority.

 

16. While fixing the sprinkler heads ensure a container is kept under the sprinkler location to receive any residual water remaining inside the pipe during testing.       

Checklist on Installation of Sprinkler































No comments:

Post a Comment

LCETED - "WHATSAPP GROUP"

For Instant updates Join our Whatsapp Group. Save our Whatsapp contact +919840140396 as LCETED and Send us a message “JOIN”

Post Bottom Ad